P&H: Land acquisition upholds Rs 4.5 Lakh/Acre Market Value, Grants 30% Severance Damages For Land Split By Drain Project

punjab-haryana
⚖️ Order Date: 01 May 2026
Headnotes

Land Acquisition Act, 1894, Ss.4, 6, 11, 18 — Determination of market value — Enhancement — Determination of market value in land acquisition matters must be based on tangible evidence such as comparable sale instances or other credible material and cannot rest on speculation -...

Land Acquisition Act, 1894, Ss.4, 6, 11, 18 — Enhancement — bifurcation of land owned by appellants — Entitlement to damages — Site plan was proved on record to establish bifurcated and same was unrebutted - Severance causes reduction in value of remaining land due...

Land Acquisition Act, 1894, Ss.4, 6, 11, 18, Civil Procedure Code, 1908, O.21 — Enhancement of compensation — Execution — Death of landowner-appellant after filing appeals — Non-impleadment of legal heirs — Liberty granted to legal heirs to seek execution by moving appropriate application before the...


Facts of the Case

P&H: Land Acquisition upholds Rs 4.5 Lakh/Acre Market Value, Grants 30% Severance Damages For Land Split By Drain Project

The Punjab and Haryana High Court has upheld the Reference Court’s determination of market value at Rs 4,50,000 per acre for land acquired to construct the Sherewala Link Drain in District Sri Muktsar Sahib, while granting 30% severance damages to landowners whose holdings were bifurcated by the project.

While deciding batch of Regular First Appeals arising from a common acquisition under the Land Acquisition. The land in Village Bam, Tehsil Malout, was acquired through notifications under Sections 4 and 6; the Land Acquisition Collector’s 2010 award assessed Rs 4,00,000 per acre, later enhanced by the Reference Court to Rs 4,50,000...

Login required to open full judgment PDF
Login to Access File