P&H: Land Acquisition - Condones 3426 days (about 9-Year) Delay; Grants Landowners Enhanced Compensation On Par With Earlier Batch, But No Interest For Delay Period The Punjab and Haryana High Court has condoned a delay of 3426 days and granted enhanced compensation to landowners in line with an earlier batch decision on the same acquisition. While court denied interest on the enhanced amount for the delayed period to balance equities. The case arises from acquisition
P&H: Land Acquisition - Condones 3426 days (about 9-Year) Delay; Grants Landowners Enhanced Compensation On Par With Earlier Batch, But No Interest For Delay Period
punjab-haryana
⚖️ Order Date:
07 May 2026
Headnotes
Limitation Act, 1963, Section 5, Land Acquisition Act, 1894, Section 54 — Condonation of delay — Delay in filing review petition is neither deliberate nor lacking in bona fides - Non-condonation of delay would result in an anomalus situation, where landowners from same acquisition would receive disparate compensation for identical lands - Enhanced compensation in terms of earlier judgment along with statutory benefits except interest for delayed period allowed. (Paras 18 and 20)
Facts of the Case
Quick Info
⚖️ Court
punjab haryana
Login required to open full judgment PDF
Login to Access File