P&H: Upholds 8% Interest Award Against Municipal Committee for Delayed Payment

punjab-haryana
⚖️ Order Date: 27 Oct 2026
Headnotes

Interest -- Part payment made before institution of suit and remaining part payment during pendency of proceedings - Determination of interest must be considered in the context of the nature of the transaction, the duration of the default and the circumstances in which the outstanding...


Facts of the Case

P&H: Upholds 8% Interest Award Against Municipal Committee for Delayed Payment

The Punjab and Haryana High Court has upheld an award of simple interest at 8% per annum against the Municipal Committee, Ratia, for delaying payment for construction materials supplied by M/s Gautam Tiles. Justice Virinder Aggarwal dismissed the Committee’s regular second appeal, finding no ground to disturb the concurrent decisions of the courts below.

Gautam Tiles had sued to recover the unpaid balance on 18 bills raised in 2014. The Committee had made a part-payment of ₹9.5 lakh in August 2014 and later paid the remaining principal during the suit, on December 30, 2016. The dispute before the High Court...

Login required to open full judgment PDF
Login to Access File